NIR CONSTRUCTION PROJECT, LLP BACKGROUND from 2006 through 2018
# |
Client |
Project Location |
Description of Works |
Work Period |
1 |
2nd Kazakhstan branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» |
Kashagan Onshore Experimental Project, Karabatan |
Precast fabrication and painting works, fabrication of reinforced concrete manholes, trays and different precast structures, details, parts |
09/2006 – 09/2008 |
2 |
ТОО «КМА Stroy Service» |
City Mall Multiplex Cinema Building, Aktobe |
Steel structure assembly and painting works, fabrication of reinforced concrete structures, sandwich panel assembly, roofing, concrete works, painting of building |
05/2008 – 01/2009 |
3 |
“MM Proje Insaat ve Danismanlik Hizmetleri Tic. Lim. Sti” Kazakhstan Branch |
“Bolashak” Business Center Construction Project, Astana |
Ceramic tiling works and pargetworks |
06/2008 – 08/2008 |
4 |
“ENKA Insaat ve Sanayi A.S.” Kazakhstan Branch |
“Essentay Mall” Building Construction Project, Almaty |
Prefabricated modular building disassembly and re-assembly, reinforced precast concrete works, scaffolding works, interior finish, electric cabling, ceramic tiling works |
12/2008 – 03/2009 |
5 |
“West Oil” LLP | Steel structured prefabricated modular building assembly at Atyrau River Port Reconstruction Project | Dismantling and re-erection of building by “turn-key”: interior finish, electrical wiring works, sanitary engineering, fire-alarm system assembly, steel structure assembly |
02/2009 – 11/2009 |
6 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch | Modular steel structured hangar building at Atyrau River Port Reconstruction Project, Atyrau | Modular building assembly by “turn-key”: concrete foundation, steel structure and sandwich-panel assembly, interior finish, electrical works |
03/2009 – 12/2009 |
7 |
«Atyrau Multi Service» LTD |
Atyrau River Port Reconstruction Project, Atyrau |
Concrete road construction, fabrication of reinforced concrete manholes, trays and curbs, drain channels; foundation blocks for placement of equipment |
04/2009 – 07/2009 |
8 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch |
CCC Camp, Karabatan |
Assembly of prefabricated modular dormitories for engineers and labor staff by “turn-key” |
05/2009 – 07/2009 |
9 |
«ARTCON» LLP |
Prefabricated dormitory assembly project at Atyrau Airport |
Package of construction works |
07/2009 – 08/2009 |
10 |
ISKER Consortium, LLP |
Atyrau River Port Reconstruction Project |
Assembly of modular building for instrument and equipment storage, production of precast reinforced concrete trays for heating system, and other concrete works |
07/2009 – 12/2009 |
11 |
«Consolidated Contracting, Engineering & Procurement S.A.L., Offshore» Company |
CCC Camp, Karabatan |
Modular hangar building with canvas cover |
10/2009 – 12/2009 |
12 |
«WEST DALA» LLP |
Reconstruction of Waste Treatment Area, Atyrau |
Concrete work package |
10/2009 – 11/2009 |
13 |
“USKO Logistics International” OJSC |
USKO Logistics Center Construction Project |
Earthworks, precast foundation, column and reservoir concreting works |
06/2010 – 02/2011 |
14 |
“AMF-1 Imstalkon” LLP |
“ADK” City Mall Construction Project, Almaty | Precast reinforced concrete floor, shaped deck assembly, concreting of columns, package of concrete and assembly works | 10/2010 – 03/2011 |
15 |
“Yalan-Atyrau” LTD |
“Yalan-Atyrau” Camp Assembly, Karabatan |
Erection of one storey prefabricated modular dormitories for 264 men |
01/2011 – 03/2011 |
16 |
“KMA Stroy Service” LLP |
Swimming pool and recreation center construction for ERSAI Caspian wharf, Mangistau Region, Kuryk village |
“Turn-key” project: earthworks, reinforced concrete foundation works, assembly of steel structures, sandwich panel assembly, roofing and etc. |
11/2010 - 03/2012 |
17 |
«Samsung Engineering Kazakhstan» LLP |
USKO Logistics Center Construction Project, Almaty |
Earthworks, precast foundation, column and reservoir concreting works |
06/2010 - 11/2011 |
18 |
2nd Kazakhstan Branch «GATE InsaatTaahhutSanayiveTicaret A.S.» |
Kashagan Onshore Experimental Project, Karabatan |
Dismantling of and packaging of steel structures |
07/2011 - 01/2012 |
19 |
“Yalan-Atyrau” LLP |
Atyrau Region, Karabatan |
“TURN KEY” Erection of prefabricated modular buildings with earthworks, 1680 m2 |
05/2012-10/2012 |
20 |
“Denholm Zholdas” LLP |
Atyrau Region, Tengiz Rotation Village |
“TURN KEY” Construction of Entire Rotation Camp (Prefabricated Modular Buildings) 6800 м2 |
06/2012 - 06/2013 |
21 |
“KMA Stroy Service” LLP |
Almaty Region, Kapchagay, “Royal Plaza” Multifunctional Entertainment Center |
Earthworks, Concrete Work Package |
07/2012 - 02/2013 |
22 |
2nd Kazakhstan Branch «GATE InsaatTaahhutSanayiveTicaret A.S.» |
Kashagan Onshore Experimental Project, Karabatan |
Warehouse, Hangar, Workshop Erection from steel structure Prefabricated Office assembly, welding works |
09/2012 - 01/2012 |
23 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch |
East Kazakhstan Region, Ayagoz area, Ore-dressing and processing enterprise |
Construction of entire rotation camp, including 46 prefabricated modular buildings, 6 steel structured buildings, PE & CS Piping, total 25000 m2 |
03/2013 - 03/2014 |
24 |
“Alsim Alarko Sanayi Tesisleri ve Ticaret A.S.”Aktogay Branch |
East Kazakhstan Region, Ayagoz area, Ore-dressing and processing enterprise |
“Turn-Key” Construction of rotation camp from prefabricated modular buildings and structures |
05/2013 - 09/2013 |
25 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch |
East Kazakhstan Region, Bozshakol Ore Deposit, for “AlsimAlarko” Company |
Prefabricated modular dormitory building by “Turn-Key” |
07/2013 - 11/2013 |
26 |
“KMA Stroy Service” LLP |
Atyrau, Kulmanova Street, behind the “Imangali” central mosque |
"Tsesna Bank" and "World Class" Recreation / Sport Center Construction (Earthworks, piling, concrete foundation works, PE and CS Piping) |
07/2013 - 06/2015 |
27 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch |
TENGIZ Rotation Camp (Vahtoviy), for KENTECH Company |
Prefabricated modular office building assembly by “Turn-Key” |
09/2013 - 12/2013 |
28 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch |
TENGIZ Rotation Camp (Vahtoviy), for KENTECH Company |
Hangar Assembly |
09/2013 - 12/2013 |
29 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch |
TENGIZ Rotation Camp (Vahtoviy), for SICIM s.P.a. Company |
Prefabricated Modular Dormitory and Canteen Assembly |
10/2013 - 04/2014 |
30 |
Kazakhstan Branch JV OJSC “Dogus Insaat ve Ticaret A.S. and Gulsan Insaat Sanayi Turizm Nak. Ve Tic.” |
Almaty Region, Enbekshikazakhskiy area |
Earthworks, concrete foundation works for temporary offices and buildings |
11/2013 - 02/2014 |
31 |
Kazakhstan Branch JV OJSC “Dogus Insaat ve Ticaret A.S. and Gulsan Insaat Sanayi Turizm Nak. Ve Tic.” |
Almaty Region, Enbekshikazakhskiy area |
Fencing Works |
11/2013 - 01/2014 |
32 |
Kazakhstan Branch JV OJSC “Dogus Insaat ve Ticaret A.S. and Gulsan Insaat Sanayi Turizm Nak. Ve Tic.” |
Almaty Region, Enbekshikazakhskiy area |
“Turn-Key” Construction of rotation camp from prefabricated modular buildings and structures including earthworks |
12/2013 - 05/2014 |
33 |
“KMA Stroy Service” LLP | Atyrau, Kulmanova Street, behind the “Imangali” central mosque | "Tsesna Bank" and "World Class" Recreation / Sport Center Construction Project (concrete work package, steel structure assembly, interior finish, scaffolding works, earthworks, casement & suspended ceiling, facade works) | 02/2014 - 09/2015 |
34 |
Treysan Prefabrik Celik Yapilar Sanayi ve Ticaret A.S. Kazakhstan Branch | Astana | ABU DHABI Construction Project, Prefabricated Modular Camp, Canteen and Mess Hall Assembly by “Turn-Key” | 03/2014 - 08/2014 |
35 | Kazakhstan Branch JV OJSC “Dogus Insaat ve Ticaret A.S. and Gulsan Insaat Sanayi Turizm Nak. Ve Tic.” | Almaty Region, Enbekshikazakhskiy area | Concrete work package, water piping system, sewage works (PE Piping), interior finish | 06/2014 - 11/2014 |
36 | "Corona Astana" LLP | Astana, “TreCronor” Restaurant Construction Project | Concrete work package | 08/2015 - 08/2016 |
37 | “KMA Stroy Service” LLP | Atyrau | Power Station Construction | 09/2014 - 12/2014 |
38 | Kazakhstan Branch JV OJSC “Dogus Insaat ve Ticaret A.S. and Gulsan Insaat Sanayi Turizm Nak. Ve Tic.” | Almaty Region, Enbekshikazakhskiy area |
Metal lattice fabrication (welding works), 250 tons |
09/2014 - 03/2015 |
39 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Tengiz | Assembly of dismantled pre-used modular prefabricated buildings as temporary offices | 12/2014 - 03/2014 |
40 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Tengiz | Concrete work package, fencing works, tank installation, workforce lease | 06/2015 - 04/2016 |
41 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Tengiz | Modification and assembly of modular camp buildings, installation and insulation of concrete blocks | 06/2015 - 02/2016 |
42 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Tengiz | Erection of pre-used dismantled modular buildings as Medical point and Emergency ambulance garage | 03/2016 - 05/2016 |
43 | “Ozen Port Production Base” LLP | Atyrau, AZTU | Fabrication and assembly of metal structures | 04/2016 - 01/2017 |
44 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» |
Atyrau Region, Atyrau-Dossor Road “GATE” JSC Base |
Erection of prefabricated buildings | 04/2016 - 08/2016 |
45 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» |
Atyrau Region, Atyrau-Dossor Road “GATE” JSC Base |
Training Center and Warehouse Construction & Installation Works | 06/2016 - 09/2016 |
46 | 3rd Kazakhstan Branch «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Tengiz | Warehouse #4 Construction & Installation Works | 06/2016 - 09/2017 |
47 | ТОО " КМА Строй Сервис" | Карагандинская обл, г. Балхаш | Строительство отделения Цесна Банк | 09/2016 - 05/2017 |
48 | PSI Строй Индустрия | г. Атырау | Восстановление частей мобильных зданий, шеф-монтаж | 08/2016 - 11/2016 |
49 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Устройство фундамента | 09/2016 - 11/2017 |
50 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | г. Атырау | Строительство и монтаж офиса на базе АО "ГАТЕ" в г.Атырау | 09/2016 - 03/2017 |
51 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» |
Атырауская область, Тенгиз |
Бетонные работы в палатках | 12/2016 - 02/2017 |
52 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Монтаж модульных зданий и склада (ремонт и монтаж быстровозводимых модульных зданий. комплекс бетонных работ, ремонт и монтаж складских помещений, укладка стяжки) | 01/2017 - 04/2017 |
53 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Комплекс бетонных работ в станции насосной | 01/2017 - 10/2017 |
54 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Предоставление услуг по комплексу бетонных работ | 06/2017 - 06/2018 |
55 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Строительство столовой для временных строительных объектов | 06/2017 - 01/2018 |
56 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, база АО "ГАТЕ", трасса Атырау-Доссор | Строительство трубного цеха | 06/2017 - 05/2018 |
57 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, база АО "ГАТЕ", трасса Атырау-Доссор | Ремонт бытовых и офисных контейнеров | 04/2017 - 01/2018 |
58 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Комплекс бетонных работ, монтаж модульных зданий, монтаж стальных зданий | 05/2017 - 05/2018 |
59 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз, TCF | Комплекс бетонных работ на объектах ТШО | 06/2017 - продолжается |
60 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Строительство гаражей скорой помощи | 11/2017 - 04/2018 |
61 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Комплекс железобетонных работ | 11/2017 - 05/2018 |
62 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Строительство столовых для временных строительных обьектов | 06/2017 - 06/2017 |
63 | 3-ий Казахстанский ф-л «GATE Insaat Taahhut Sanayi ve Ticaret A.S.» | Атырауская область, Тенгиз | Комплекс бетонных работ (устройство фундаментов зданий, бетонирование пешеходных дорожек и другие бетонные работы на объекте) | 06/2017 - 08/2018 |
64 | ТОО "KAZENCO" | Атырауская область, Тенгиз, Прорва для компании SARENS | Строительство рабочего городка | 02/2018-08/2018 |